Mermaid Gantt Chart for a Project Plan

Mermaid Gantt Chart for a Project Plan

Watch on YouTube Subscribe

Type a project plan and let Mermaid draw the Gantt chart: sections, tasks, dates, dependencies with after, and a go live milestone. A gift card release for an online shop, made in the free Mermaid live editor.

Step by step

Plans as text

  1. Gantt from text. A Gantt chart shows what happens and when. In Mermaid you type the plan as text and the bars draw themselves. The example is a release plan for a new gift card feature in an online shop.

Set up

  1. Diagram type. In the Mermaid live editor, clear the editor and type gantt on the first line. On the next line, add the title: title Gift card release.
    gantt
        title Gift card release
  2. Date format. Add dateFormat YYYY-MM-DD. It tells Mermaid how you write your dates. Year-month-day is the safest choice because it can't be confused with day-month or month-day.
        dateFormat YYYY-MM-DD

Tasks

  1. Sections and tasks. Type section Analysis to start a group. Then add a task: a name, a colon, a short ID, a start date and a length, like Gather requirements :a1, 2026-11-02, 5d. 5d means 5 days. The preview now shows the first bar, 5 days long, under the Analysis section.
        section Analysis
        Gather requirements :a1, 2026-11-02, 5d
  2. Dependencies. Instead of a start date, write after and an ID. Sign off scope :a2, after a1, 2d starts when a1 ends and takes 2 days. If you change a1, every task linked after it moves too. Add section Build with two linked tasks. Build gift cards :b1, after a2, 10d takes 10 days after sign-off. Test with users :b2, after b1, 4d adds 4 days of testing with real users.
        Sign off scope :a2, after a1, 2d
        section Build
        Build gift cards :b1, after a2, 10d
        Test with users :b2, after b1, 4d

Milestone

  1. Milestone. Add section Launch, then Go live :milestone, after b2, 0d. The milestone tag and a length of 0d tell Mermaid this is a single point in time, so it draws a diamond instead of a bar. The finished chart has 3 sections, 4 tasks and a go live milestone. The diamond marks go live. Because it is linked with after b2, it moves by itself if any task before it slips.
        section Launch
        Go live :milestone, after b2, 0d

Recap

  1. The rules. The rules: set the date format, group tasks in sections, link them with after, and mark the finish with a milestone.

Common mistakes

  • Expecting 5d to mean 5 working days. By default Mermaid counts calendar days, so Saturdays and Sundays are included. Add excludes weekends on its own line after dateFormat to skip them.
  • Dates that don't match dateFormat. If you set dateFormat YYYY-MM-DD but type 02/11/2026, Mermaid can't read the date and the chart breaks or the bar lands in the wrong place. Write every date in the format you declared, like 2026-11-02.
  • Using after with no ID to point at. after can only link to a task that has an ID, and the ID must be typed the same way, like a1. Give every task you plan to link to a short, unique ID.
  • A colon inside the task name. Mermaid treats the first colon as the end of the task name, so a name like Phase 1: Build breaks the line. Leave colons out of task names.

When a business analyst uses this

In a planning workshop, a business analyst can type the analysis, sign-off, build and test tasks into Mermaid while the team watches and get a timeline on the spot. If sign-off slips by 3 days, changing one length moves every linked task and the go live milestone, so the plan stays honest.

Questions people ask

How do I skip weekends in a Mermaid Gantt chart?

Add the line excludes weekends after dateFormat. Mermaid then leaves out Saturdays and Sundays when it works out task lengths.

How do I add a milestone in a Mermaid Gantt chart?

Put milestone first after the colon and give it a length of 0d, like Go live :milestone, after b2, 0d. Mermaid draws it as a diamond.

Can a Mermaid task start when another task ends?

Yes. Write after and the other task's ID instead of a start date, like :a2, after a1, 2d. The task then moves whenever the earlier task changes.